Barriers down and no trains running. That’s what to expect for long periods this autumn.

Six crossings in Liss, Petersfield, Tilmore and Sheet are affected between the end of September and November.

The crossing at Liss Common will be shut for four weeks from 27 September until 24 October.

Upgraded equipment and new barriers are being installed. Network Rail says it will make local level crossings safer but slower.

You’ll be waiting for up to 2 minutes and 24 seconds longer every time the barriers close.

Safer but slower

At some crossings the old half barriers will be replaced by full barriers. It will mean longer waits while trains pass.

In Sheet and at Kingsfernsden Lane between Tilmore and Ramshill the wait will be more than four times longer than it is at the moment.

Kingsfernsden Level Crossing between Ramshill and Tilmore. These old barriers are on their way out.

A “nine day blockade” is the language being used by railway managers to describe the closures. Replacement buses will be running while the tracks are closed to trains.

Henry Davis from Network Rail is speaking to Shine Radio’s Stephen Martin at Liss railway station.

Henry Davis from Network Rail

Estimated wait time increases

Network Rail says you’ll wait longer for the barriers to lift after the new technology is in place.

CrossingAverage waiting time nowWaiting time after the changesWait change
Petersfield railway station3’18”3’24”6″ longer
Liss railway station3’53”3’53”No change
School Lane Sheet44″3’07”2’23” longer
Kingsfernsden Lane42″3’06”2’24” longer
Princes Bridge1’16”2’54”1’38” longer
Liss Common48″2’50”2’02” longer

Data: Network Rail estimates. Indicative and may vary with service patterns and time of day.

Full closure schedule

Petersfield level crossing will only be closed overnight. The others will be 24 hour closures.

CrossingWork startsWork ends
Petersfield railway stationSaturday 25 OctoberSunday 2 November
Liss railway stationSunday 26 OctoberMonday 3 November
School Lane SheetSaturday 25 OctoberMonday 3 November
Kingsfernsden LaneSaturday 4 OctoberFriday 24 October
Princes BridgeSaturday 11 OctoberSaturday 25 October
Liss CommonSaturday 27 SeptemberFriday 24 October

When are trains replaced by buses?

Saturday 25 October and Saturday 1 NovemberThere will be three buses every hour running between Havant and Haslemere and stopping at Petersfield. One bus per hour will call at Liss.
Sunday 26 October and Sunday 2 NovemberThere will be two buses every hour running between Havant and Haslemere and stopping at Petersfield. One bus per hour will call at Liss.
Monday 27 October to Friday 31 OctoberThere will be three buses every hour running between Havant and Haslemere and stopping at Petersfield. One bus per hour will call at Liss.

A train passing through Petersfield railway station